Record a quote you made outside ONYX1
Upload a quote you wrote in another program, enter its value and GST, and the job treats it as its accepted quote.
On this pageBefore you start
Use this when you quoted a job somewhere else, such as a spreadsheet, a supplier's template or another app, and the customer has already agreed to it. You upload the quote file and enter its value. ONYX1 then treats it as the job's accepted quote, so the job can go ahead and you can turn the quote into an invoice.
Before you start
- Only the owner, admins, dispatchers and office staff can add an outside quote. Site supervisors, techs and contractors cannot see outside quotes or their files.
- The job must already exist and must not be archived.
- Have the quote file ready: a PDF or a photo (JPEG, PNG or WebP), up to 20 MB.
Add an outside quote
- Open the job and select the Money tab.
- In the Quotes card, select Add outside quote.
- Under Quote file, choose the PDF or photo of the quote.
- Enter the Quote value in dollars, for example 1,150.00.
- Under GST, choose how that value relates to GST: The value excludes GST (add 15%), The value includes GST or Zero-rated (no GST). The line under it shows the amount excluding GST, the GST and the total.
- If the quote has its own number, enter it in Your quote number.
- If you know what the job will cost you, enter it, excluding GST, in Job cost. ONYX1 saves it as the job's budget (see Edit a job). If the job already has a budget, the hint under Job cost shows it, and the cost you enter replaces it. Leave Job cost blank to keep the budget as it is. On a finished job, Job cost is turned off: a finished job's cost cannot change.
- Select Add quote. Until the file and the value are in, the button stays unavailable and a line beside it says what is still needed.
If the job already has a quote or an invoice
If the job already has an accepted quote, or has already been invoiced, the dialog warns you. It names each accepted quote with its total, and says when the job has already been invoiced. Converting a second quote raises a second invoice, so add one only for extra work, such as a variation. To go ahead, tick Add another quote to this job, then select Add quote.
What happens next
The quote appears in the job's Quotes card with an Outside quote badge and an Open file link. It is saved as an accepted quote, so:
- if Jobs can't be scheduled until the client accepts the quote is on in Settings → Security, the job can now be scheduled and started
- Convert to invoice works as it does for any accepted quote. The draft invoice has one line, "As per quote" followed by your quote number, at the value you entered, with the same GST treatment. See Invoice a job.
In Sales, the quote carries an Outside badge and gets an ONYX1 quote number like any other. You can also find it by searching for your own quote number. Its progress shows one step, Accepted outside ONYX1, with the day you added it.
Opening the full quote shows a link to your file (Open followed by the file name), the GST treatment and the totals, in place of an ONYX1 quote document. A photo is also shown on the page; a PDF opens from the link. Open quote file, beside the other buttons, opens the file too.
ONYX1 never sends an outside quote to your customer, and it does not appear in their client portal. Because of that, an outside quote has no Send, Copy customer link, Edit, Mark as sent, Mark declined, Reopen or job change. It stays on the job you added it to.
Fix a mistake
You cannot change an outside quote's value, GST treatment, number or file, and you cannot delete it. To replace it, add the corrected quote to the job (tick Add another quote to this job), then ask the owner or an admin to archive the wrong one (under More on the quote).
If you already converted the wrong quote to an invoice, archiving the quote does not touch that invoice: void the invoice as well (see Invoice a job).
Warning
Archiving takes the quote off the job's Quotes card and out of the Sales list, but the job still counts it as an accepted quote. If Jobs can't be scheduled until the client accepts the quote is on, an archived outside quote still lets the job be scheduled.
If something goes wrong
- Enter the quote value: more than zero, up to one million dollars, with at most two decimal places. The value is zero, too large, not a number or has more than two decimal places.
- That file is over the 20 MB limit. Choose a smaller file, or save the quote as a smaller PDF.
- Choose a PDF or a photo (JPEG, PNG or WebP). Other file types are not accepted.
- This job is finished, so its cost can't change. Leave Job cost blank to add the quote. Leave Job cost blank; the quote itself can still be added.
- Enter the job cost in dollars and cents, up to ten million dollars, or leave it blank. The cost has more than two decimal places, is too large or is not a number.
- This job already has an accepted quote or an invoice. Tick Add another quote to this job to add this one as well. See If the job already has a quote or an invoice.
- Leave Job cost blank, or enter more than zero. A cost of zero is not accepted, so a budget is never wiped by mistake.
Use only letters, numbers, spaces and - _ / . , ' # : ( ) & + in the quote number.The number contains another character, such as a curly apostrophe, an en dash or a hidden character. Use only the characters the message lists.- This quote was made outside ONYX1, so it can't be sent, shared, edited, reopened or moved. To replace it, add a corrected quote, then archive this one. You tried an action that only an ONYX1 quote has.